Update on the new Pre-school building.

We still have a couple of issues with the lease that need ironing out but we are hopeful that works will commence the week of February half term (19th – 26th).

Demolition of the existing building is expected to begin on 19th February & take 2/3 days and the initial groundworks a further 3-4 days.

At this point we will be in a position to accept delivery of the new building the following week.

The onsite build time for this is no more than 3 days.

Once the building has been delivered the new play area will be resurfaced and these further groundworks will continue into the following week.


Submitted by: Kirsty Jay, Brereton Pre-School